Projects

Level 1 B-BEEE, CIDB Member
Nov 2024

Decanter Space Civil work

The project was completed at SAB Alrode(South African Breweries) . The company generated R7 000 000, duration of the project was 6 months.
Nov 2024

Sceptic Tanks Supply and Installation.

This project was completed in November 2024 and it took 2 months to complete it. It generated R421 000. This was still at SAB Alrode.
2025

Boom Access Gates and Barriers

This project generated +- R2 000 000. This project took 2 months to complete in 2025 at SAB Alrode.
2025

Slab construction at SAB Alrode

The project took around 2-3 weeks to complete while generating R1 500 000. Pictures linked to this project are attached.
2025

Air Conditions and Extractor Fans Supply and Installation

The project took a week to complete and generated R300 000 therein.